City of Boynton Beach Utility Department - Capital Improvement Program
SE Federal Highway Project
Current Status Date: February 5, 2009
Current Location: Boynton Isles to Riviera Drive
Project Contacts: Paul Fleming, Project Manager, City of Boynton Beach (561) 742-6487 Clifford Rockey, Inspector, City of Boynton Beach (561) 742-6409 Dave Mathews, Project Engineer, Mathews Consulting (561) 478-7961 Alex Ballum, Project Inspector, Mathews Engineering, (561) 307-2875
Description: This project will consist of replacing the existing water main and replacing it with approximately 4,800 linear feet of 6" ductile iron pipe water main. Included are service connections and fire hydrants. In addition to the water main replacement are storm water improvements. The storm water improvements consist of approximately 1,000 linear feet storm water pipe, inlet boxes and swale construction. The project should take approximately 4 months and should be complete around March 30, 2009.
Current Status: This project is completed. We thank you for your patience and cooperation during the construction.
|