Arts Culture & LearningAmerica's GatewayCatch a WaveShopping Dining & Entertainment 

 

 

UTILITY IMPROVEMENT PROJECTS

UTILITIES DEPARTMENT - SUMMARY OF KEY IMPROVEMENT PROJECTS

Harbor Estates Neighborhood Improvement Project

The Harbor Estates Neighborhood experiences periodic roadway flooding and standing water during heavy rainfall events, which has affected the residential property owners located in the vicinity of North and South Roads. To improve the quality and reliability of the Harbor Estates Neighborhood Utilities, the City of Boynton Beach will provide a new stormwater system that will collect the stormwater and discharge through four (4) shallow outfalls located along the north edge of North Road and one (1) shallow outfall at the southeast corner of the neighborhood. The project will also include replacing aging and undersized water mains and upgrading fire hydrants in the project area. A new roadway and curbing will also be provided. 
The City of Boynton Beach has contracted with the Civil Engineering Firm, Mathews Consulting, Inc., to design and permit these utility improvements. The project is currently in the 90% design stage and will be moving into the final permitting stage after this Public Meeting.

The third Public Meeting was held at City Library Program Room, 208 S. Seacrest Blvd. on Wednesday, February 15, 2017 from 6:30 - 8:00 pm.

Below is a link to the 90% design plans available for review and the overall project brochure:

90% Design Plans

Project Brochure II

 

Ion Exchange Resin Plant and East Water Treatment Plant Improvements

This Boynton Beach Ion Exchange project will increase the capacity of the East Water Treatment Plant to 24 mgd and provide an ion exchange resin system for polishing of the water quality, specifically for removal of color and organic carbon. Work will include rerating of the lime softeners; valve and actuator replacements; a new ion exchange system; and a new transfer pump station, ground storage tank, and high service pump station.

Learn more about this exciting new project and follow the Project Updates, Calendar & Schedule, Outreach Programs and view Maps & Photos:

Ion Exchange Resin Plant & EWTP Improvements

August/September Montly Update

Central Seacrest Corridor Neighborhood Utility Improvements – Phase II Bid Award

The goal of the project is to replace aging and undersized water mains and improve drainage within the right of way.  The project will add 38 hydrants and replace 15 existing hydrants with the new standard hydrant which improves water security and new driveway aprons.  The City went out to bid for the project and Man-Con, Inc. was determined to be the lowest, most responsive bidder. The project includes a 10% contingency for unknown conditions for a Total Contract Budget of $8,957,270.85.

The Current Project Schedule is as follows:

  • Commission Approval of Award: August 5, 2014
  • Notice to Proceed: September 15, 2014
  • Complete Review of Shop Drawings: November 3, 2014
  • Begin Construction Activities: November 10, 2014
  • Substantial Completion: March 15, 2016
  • Final Completion: April 15, 2016

The Utilities Department will conduct a full-scale Customer Outreach for the project that will include two neighborhood informational meetings.  Brochures and door hangers will be placed at each residence in the construction area prior to construction activity.  There will be daily construction updates on Facebook as well as Twitter updates for road closures and construction activity.  A complaint line will be available for residents to call City and Contractor staff directly, with immediate response to concerns and complaints.  City staff will track and document all outcomes and resolutions.

PROJECT UPDATES:

  Central Seacrest Corridor Neighborhood Utility Improvements Update

  Central Seacrest Corridor Customer Outreach Letter  

  Central Seacrest Corridor Informational Brochure

 

2